Adani Godda Energy Plant: BPDB to pay Rs 1,219.1 cr for not utilizing electrical energy


If it does not add worth, it is nugatory, stated the seminal American industrialist Henry Ford. And this quote finest describes the state of affairs the Bangladesh Energy Improvement Board finds itself in in its cope with India’s Adani Energy.

Engineered throughout the first go to of Indian Prime Minister Narendra Modi to Bangladesh in 2015, Adani Energy has put in 1,600MW of thermal energy to provide a lot of the energy generated to the BPDB by a devoted transmission line in Godda, Jharkhand.

Observe Day by day Star’s Google Information Channel for all the newest information.

That energy plant can be going into manufacturing from August however its transmission will not be prepared till at the very least December, that means the ability can be wasted.

And but, in accordance with the “Adani Godda Coal Energy Plant: An Achilles Heel of Bangladesh’s Energy Sector” report, BPDB must pay a capability cost of $141.1 million, or Rs 1,219.1 crore, for the 4 months to December.

Capability price is a penalty paid to the plant proprietor for failure to buy a sure portion of available electrical energy.

As per the settlement signed in 2017, Adani Energy will provide 1,496 MW of electrical energy for 25 years from December 2021.

As a result of pandemic, the Adani Group subsidiary has prolonged the launch date by six months. The ability plant is all set to begin industrial operation in August.

However Bangladesh’s Energy Grid Firm (PGCB) stated extra time is required to organize the infrastructure for importing energy. This yr will probably be at the very least December.

As per the settlement, Adani Energy will arrange a 106 km lengthy 400 kV transmission line from Godda to the interconnection level.

For point-to-point energy relay, the PGCB undertook a Rs 225.2 crore challenge to construct a 28 km transmission line from the India-Bangladesh border to Rohanpur substation in Bangladesh.

The substation is but to be constructed because the supplies haven’t arrived, Mohamed Mizanur Rahman Sarkar, the transmission line’s challenge director, advised The Day by day Star.

“We will import round 800 MW of energy within the early months of subsequent yr,” he stated.

BPDB has agreed to pay Rs 3.26 per unit capability price to the Adani Godda energy plant. The capability cost for comparable crops in Bangladesh is Rs 2.83.

Minister of State for Energy, Vitality and Mineral Sources Nasrul Hamid isn’t but positive whether or not the BPDB must pay a capability price for 4 months that electrical energy isn’t imported from Adani Energy, which was based by Gautam Adani, the world’s largest energy producer. The fifth firm richest individual.

“However even when we had constructed it ourselves and used no electrical energy, we might nonetheless have needed to pay for the capability.”

He advised The Day by day Star that the federal government’s coverage of ‘no electrical energy, no pay’ for impartial energy producers on such a big scale isn’t relevant.

“If we implement this, nobody will conform to construct the plant. Adani will make investments and we now have to provide them minimal returns. If we do not take energy, they are going to be in hassle,” Hamid stated.

For drawing energy from Godda coal energy plant, BPDB will get rid of its common ‘advantage order dispatch’ methodology and go together with ‘priority-based dispatch’.

Below the ‘advantage order dispatch’ methodology, energy crops supplying low cost electrical energy are given the primary likelihood of manufacturing.

However underneath the ‘priority-based dispatch’ methodology, imported energy can be first transmitted whereas retaining the home energy crops idling, even when they generate electrical energy at a less expensive fee.

So electrical energy from Adani Godda can be 56.2 % dearer than different imported energy, 36.9 % greater than imported coal energy and 4.3 % greater than home coal energy, in accordance with the Bangladesh Working Group on the Exterior Debt and India-Based mostly In line with the research carried out. Growthwatch.

Bangladesh must pay over Rs 1 lakh crore as capability price to the Adani coal energy plant over the 25-year lifetime of the settlement, which is sufficient for the development of three Padma bridges, the research revealed on Monday stated.

In a worst-case situation, BPDB must pay $423.3 million (Rs 3,657.2 crore) and $11.01 billion (Rs 108,360.6 crore) yearly in capability prices over the 25-year working lifetime of the plant.

The report stated that the Padma Bridge was constructed for $3.87 billion, the Dhaka Metro Rail for $2.59 billion and the Karnaphuli River Tunnel for $1.22 billion.

In a best-case situation, the annual capability price payable to the Adani Godda energy plant can be $331.66 million (Tk 2,865.55 crore), whereas the lifetime capability price would attain $8.62 billion (Tk 84,9037 million).

In line with the report, Adani Energy must pay again its funding in a most of six years and a minimal of 4.67 years.

“The capability prices will rely on the provision of the ability plant. If the ability plant runs with 85 per cent Plant Load Issue (PLF), will probably be the best situation and the ability plant might drop its PLF at 53 per cent, which is the bottom Common in India,” stated Hasan Mehdi, one of many report’s authors.